What to ask before you book AI capacity in New South Wales
A GPU booking in New South Wales now needs a power, water and connection story you can defend, because the state's data centre report is in and the rules under it are still moving.
6 min readDynacore
Cite this briefing as https://dynacore.com.au/insights/what-to-ask-before-you-book-ai-capacity
Whether the building can deliver the power and reject the heat is still the first test, set out in Power, cooling and the building in front of you. For a booking that will run in New South Wales, or with a supplier whose price depends on a facility there, the connection, the water and the power contract are part of the product as well.
On 5 November 2026 the NSW Legislative Council Public Accountability and Works Committee tabled Report No. 10, Data centres (opens in a new tab). The government's response is due on 5 February 2027. The report is advice. It is not a statute, and tabling it does not rewrite a consent. It sits on rules already published, and on standards the Commonwealth has said it intends to legislate.
This briefing is general information for CIOs, CTOs, and infrastructure and data leaders. It is not legal advice, and it is not a forecast of a power bill.
A connection request is not a load you can book
The Australian Energy Market Operator's 2026 Electricity Statement of Opportunities (opens in a new tab), published on 25 August 2026, forecasts data centre electricity consumption in the National Electricity Market rising from approximately 5 terawatt-hours in 2025-26 to 34 terawatt-hours by 2035-36. That is from around 3 per cent to approximately 13 per cent of electricity supplied through the grid. The same release says the method now allows for projects that drop out, for the difference between connection capacity and actual use, and for demand that ramps up over years rather than arriving on day one.
The NSW Data Centre Guidelines (opens in a new tab) of August 2026 put a number on the gap between a request and a built facility. They cite Oxford Economics, which prepared AEMO's data centre forecast, for an estimate that 6 in every 7 megawatts of connection requests are phantom demand. They also record that energy utilities suggest 20 per cent of applications in their pipeline are likely to proceed. Those are different estimates. Ask which megawatts are contracted, which are only in discussion, and which are a form in a queue.
The NSW Government's page on data centre network connections (opens in a new tab) states that, as of July 2026, data centres were seeking network connections of up to 28 gigawatts, of which around 13 gigawatts were in advanced discussions. The page says 13 gigawatts is more than the average daily electricity demand in NSW. That comparison is about connection capacity sought, not about electricity those facilities are using. A proposal that quotes the queue is quoting the wrong object.
What an assessment in New South Wales already asks
The guidelines are the state's assessment standard. Applicants are expected to show whether they comply, and commitments a consent adopts become conditions of that approval. The guidelines do not rewrite every hall already running. The figures below are theirs, and a consent can adopt, vary or stage them, so read the approval for the facility in the proposal.
Additional supply, with firming. Performance measure 13 asks a proponent to enter power purchase agreements and firming agreements for additional renewable generation in New South Wales, enough to meet the facility's electricity demand. At least 40 per cent of that energy is to be wind. Storage, as a battery or pumped hydro, is to be at least 25 per cent of generation capacity and able to run for four hours. From the fourth year of operation, contracted supply is to equal annual average demand, and to rise as the load ramps. Agreements run for at least ten years, and they are for projects that had not reached a final investment decision when signed. A short-term mismatch can be covered with renewable energy guarantee of origin certificates, or the equivalent, and those certificates still have to meet the wind, storage and location conditions.
A two-hour reduction, and diesel does not count. Performance measure 9 asks the facility to show it can cut grid-supplied demand by 25 per cent of forecast average load for up to two hours. Shift load first, including programmable compute. Then use on-site or nearby generation and storage. The notice period is agreed with the utility, and the guidelines say AEMO may instruct a reduction in line with it. Diesel backup does not count.
Water, and a connection that might not be fully used. Facilities that cool with water are pointed toward recycled water, and toward a design that can cut the use of drinking water if drought restrictions are imposed. Where recycled water is not available, performance measure 14 requires a plan with the utility to offset interim use of drinking water, by funding supply, by an efficiency program, or by a closed-loop system. Performance measure 11 asks for a commercial agreement so other customers do not fund the water works. Performance measure 10 asks for arrangements that stop a half-used connection asset landing on everyone else's bill: prepayments, take-or-pay terms, capital contributions or guarantees, to the extent the rules allow.
The energy page linked above says the Electricity Infrastructure Investment Amendment Bill 2026 has been passed so that cost-recovery regulations can be made, and that those regulations are still to come. Until they are in force, the contract is the protection you can read.
The Commonwealth frame is wider than one state. The Expectations of data centres and AI infrastructure developers (opens in a new tab), published on 23 March 2026, ask new or expanded developments to bring additional clean generation or storage, pay their share of network costs, stay flexible at peaks, and use water efficiently. Large-scale compute providers are also expected to offer capacity to Australian research and smaller firms on favourable terms. A small on-site enterprise room is outside those expectations. A hall you depend on for production may not be. On 15 July 2026 the Prime Minister's media release (opens in a new tab) said national standards for large data centres would be legislated early the following year, including underwriting new supply, paying connection costs, reducing power when asked, and using water efficiently. That statute is not in force. A multi-year booking still has to be able to live with it.
What to do with the November report
Tabling the report does not turn measure 13 into an hourly match, and it does not replace a one-facility consent with a cumulative one. Two accounts from that week describe a tighter test than the guidelines. CNA (opens in a new tab), on 5 November, quotes the finding that planning assesses data centres primarily as individual developments, despite many impacts being cumulative. PV Tech (opens in a new tab), on 6 November, reports that recommendation 11 asks the state to require demand to be met with the operator's own renewable energy on an hourly basis, at a minimum. Those are accounts. The text to contract from is the report (opens in a new tab), read with counsel.
Until the response on 5 February 2027, test the facility against measures 9, 10, 13 and 14. A supplier who cannot place the hall against those measures cannot tell you how a tighter test would land. Ask while the term can still say what happens if the rules change.
Questions worth writing into the order
- What is the connection capacity, the expected operating load, and the load you are contracted to? Which of the three is the number in the proposal?
- Is the renewable supply additional generation in New South Wales, with the wind share and the four-hour storage the guidelines describe, or an annual certificate? From which year does supply equal demand?
- Can the facility cut grid demand by 25 per cent of forecast average load for two hours without diesel, and which workloads move?
- What water does the cooling use, and what happens under restrictions?
- Who pays if a connection asset is built and the load does not arrive?
- If the February response tightens the test, what happens to your term?
Outside New South Wales, ask the same questions in that jurisdiction's words, and against the Commonwealth expectations. An AI factory is still defined by the output, the data and the building, as set out in What an AI factory is, and how to plan one. These questions decide whether the facility can keep that output inside the conditions already published, and inside any tighter conditions the February response may add.
Dynacore's AI Factory work starts from the workload and the site together. If you are booking capacity and you want these questions in one briefing, use the contact page.